Final | 8/9/2018 | 8/13/2018 | 8/13/2018 | A | PASS |
James Ady
|
|
|
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Permit ELE18-03001 has been purchased for the EV circuit. Thank you. Inspection requested via web by Rob Maes final ok
|
Final | 8/8/2018 | 8/8/2018 | 8/8/2018 | A | NH |
Rock A. Hudson
|
|
|
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes Called contact to see if owners were going to be home, he called and did not get answer, I instructed them to set up appointment with owner for access and recall.
|
Electrical Rough-In | 8/6/2018 | 8/7/2018 | 8/7/2018 | P | PASS |
Rock A. Hudson
|
|
|
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes Contractor to pull permit for car charging circuit on south east wall. New micro handle more capacity. All listing confirmed. Rough in ok
|
Issue PAID IN FULL permit | | | 7/24/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/24/2018 | | DONE |
|
|
|
This permit was created on the web by Rob Maes
|