First Notice | 9/6/2018 | 9/6/2018 | 5/29/2020 | | DONE |
Tom Saunders
|
|
|
This permit finaled on the web by Tim Dunlop
|
Final | 9/5/2018 | 9/6/2018 | 9/6/2018 | A | PASS |
Tom Saunders
|
|
|
final on LEDs Phone #: ###-#### Inspection requested via web by Tim Dunlop...job complete..ok to final
|
Electrical Rough-In | 8/31/2018 | 9/4/2018 | 9/4/2018 | A | PASS |
Tom Saunders
|
|
|
LED rough in. Will be in north bay doing LED highbay installs in morning Phone #: ###-#### Inspection requested via web by Tim Dunlop...UL listed equipment verified...offices complete..2 warehouses 37 lights
|
Issue PAID IN FULL permit | | | 8/24/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/24/2018 | | DONE |
|
|
|
This permit was created on the web by Tim Dunlop
|