First Notice | 1/10/2019 | 1/10/2019 | 2/5/2019 | | DONE |
Tom Saunders
|
|
|
This permit finaled on the web by David Feller
|
Final | 1/9/2019 | 1/10/2019 | 1/10/2019 | A | PASS |
Tom Saunders
|
|
|
Parking lot fixtures Phone #: ###-#### Inspection requested via web by David Feller... poles complete...ok to final
|
Electrical Rough-In | 9/3/2018 | 9/4/2018 | 9/4/2018 | A | PASS |
Tom Saunders
|
|
|
Underground / trenching inspection for parking lot Phone #: ###-#### Inspection requested via web by David Feller...underground for 12 new parking lot lights...using existing circuit off light pole
|
Issue PAID IN FULL permit | | | 8/27/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/27/2018 | | DONE |
|
|
|
This permit was created on the web by David Feller
|