Print Statement | | | 6/11/2019 | | DONE |
|
|
|
|
Final | 12/28/2018 | 12/31/2018 | 12/31/2018 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Tyler Bowen... ok to final Taco Bell supplied signage...contractor hooked up...UL listing and discoonect-ok
|
Electrical Rough-In | 12/14/2018 | 12/17/2018 | 12/17/2018 | A | PASS |
Rock A. Hudson
|
|
|
ceiling cover Phone #: ###-#### Inspection requested via web by Tyler Bowen Grid rough in ok cover
|
Permanent Service | 11/15/2018 | 11/16/2018 | 11/16/2018 | A | PASS |
Tom Saunders
|
|
|
Contact is John Bronson at ###-#### Phone #: ###-#### Inspection requested via web by Steve Blackmer... p/s u/g new ok
|
Electrical Rough-In | 11/12/2018 | 11/13/2018 | 11/13/2018 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Tyler Bowen Walls and hard lids ok to cover
|
Electrical Rough-In | 9/24/2018 | 9/25/2018 | 9/25/2018 | A | PASS |
James Ady
|
|
|
John. Underslab. Phone #: ###-#### Inspection requested via web by Sean DeLacy Main electrical room. Underground only ok to cover
|
Electrical Rough-In | 9/12/2018 | 9/13/2018 | 9/13/2018 | A | PASS |
Eric Story
|
|
|
John. Underground pole base ; drive thru bases. Phone #: ###-#### Inspection requested via web by Sean DeLacy U/G for parking lot and ordering board and secondarys ok to cover
|
Electrical Rough-In | 8/27/2018 | 8/29/2018 | 8/29/2018 | A | PASS |
Tom Saunders
|
|
|
Ufer inspection. Ufer will be installed Tuesday Afternoon, and the concrete pour will be on Wednesday Afternoon. Please call John ###-####. Thank You Phone #: ###-#### Inspection requested via web by Steve Blackmer...ok to cover
|
Issue PAID IN FULL permit | | | 8/27/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/27/2018 | | DONE |
|
|
|
This permit was created on the web by Steve Blackmer
|
First Notice | 12/31/2018 | 12/31/2018 | | | |
Tom Saunders
|
|
|
|