Final | 10/24/2018 | 10/25/2018 | 10/25/2018 | A | PASS |
Eric Story
|
|
|
final on shop Phone #: ###-#### Inspection requested via web by Brian Hughes Final for detached shop only ok
|
Permanent Service | 10/23/2018 | 10/24/2018 | 10/24/2018 | P | PASS |
Tom Saunders
|
|
|
changing out meter base to feed the shop. Installing a 200 amp all in one. Power shut off with Idaho power at 9 am. need ok to energize for them to do a reconnect. Phone #: ###-#### Inspection requested via web by Brian Hughes..
p/s u/g reconnect ok
|
Rough-In Permanent Service | 8/29/2018 | 8/30/2018 | 8/30/2018 | A | PASS |
Tom Saunders
|
|
|
Panel not energized. will be changing out meter base on house to a 320 amp base and feeding shop. will be doing this at a later day. Just need shop rough in for cover at this point. please call me with questions. gate open on right to go back to shop. Phone #: ###-#### Inspection requested via web by Brian Hughes...
no service at this time rough ok to cover underground to shop from service never inspected...contractor taking responsibility...under concrete drive
|
Issue PAID IN FULL permit | | | 8/29/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/29/2018 | | DONE |
|
|
|
This permit was created on the web by Brian Hughes
|