First Notice | 10/23/2018 | 10/23/2018 | 11/14/2018 | | DONE |
Rock A. Hudson
|
|
|
This permit finaled on the web by Tom Jenkins
|
Final | 10/23/2018 | 10/23/2018 | 10/23/2018 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins Final ok
|
Permanent Service | 10/17/2018 | 10/18/2018 | 10/18/2018 | A | PASS |
Daryl DeGrange
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins p/s u/g rec ok
|
Conference | 8/31/2018 | 8/31/2018 | 8/31/2018 | A | DONE |
Rock A. Hudson
|
|
|
Need conference with owner and Idaho Power at 10am if you can make it. Please let me know. Phone #: ###-#### Inspection requested via web by Tom Jenkins Discussed options to refeed service after service change. From Idaho Power vault into basement electrical room. With room all concrete with steel fire door ok to LB and pipe down inside room to allow electrtical equipment to legal height. Setting CT can and main disconnect and gear to refeed building loads. Door to electrical room to open out and have panic hardware installed. East portion of building to be fed seperately and shall have seperate service due to seperate address and seperated by firewall.
|
Issue PAID IN FULL permit | | | 8/31/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/31/2018 | | DONE |
|
|
|
This permit was created on the web by Tom Jenkins
|