Conference | 11/6/2018 | 11/6/2018 | 11/6/2018 | P | DONE |
Mark Moncarr
|
|
|
This is a project where the customer and I have not been able to agree upon finishing. Rough-in electrical is partially done however I need it inspected so I can walk away. Please call me 1 hour in advance to ensure I can be on site. Phone #: ###-#### Inspection requested via web by Casey Fouts Misc. electrical work done throughout main level, basement and garage. Contractor is going to end his electrical contract. No more work is going to be done at this time. Contractor is going to note areas where work was started and or completed in rough-in areas. During conversation it was mentioned that the property owner needed to hire another licensed electrical contractor to resume electrical work under a new electrical permit.
|
Electrical Rough-In | 11/5/2018 | 11/6/2018 | 11/6/2018 | A | CANC |
Mark Moncarr
|
|
|
This is a project where the customer and I have not been able to agree upon finishing. Rough-in electrical is partially done however I need it inspected so I can walk away. Please call me 1 hour in advance to ensure I can be on site. Phone #: ###-#### Inspection requested via web by Casey Fouts Changed RI inspection to a conference. Contractor to end work with current property owner. During conversation, it was mentioned that the property owner needs to hire another licensed electrical contractor to take over work that has been done.
|
Permit EXPIRED | | | 11/6/2018 | | DONE |
|
|
|
contractor stopped working on project and new contractor took over see ELE18-04705
|
Issue PAID IN FULL permit | | | 9/28/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/28/2018 | | DONE |
|
|
|
This permit was created on the web by Casey Fouts
|