First Notice | 11/28/2018 | 11/28/2018 | 1/18/2019 | | DONE |
Tom Saunders
|
|
|
This permit finaled on the web by Stacie Tasker
|
Print Statement | | | 1/16/2019 | | DONE |
|
|
|
|
Final | 11/28/2018 | 11/28/2018 | 11/28/2018 | P | PASS |
Tom Saunders
|
|
|
Jacob is the site contact.Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker...
ok to final no card onsite
|
Electrical Rough-In | 11/5/2018 | 11/6/2018 | 11/6/2018 | A | PASS |
Mark Moncarr
|
|
|
We need a ceiling inspection. Jacob is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Ok cover ceilings in 4 offices S side, and conference rm N side.
|
Electrical Rough-In | 10/8/2018 | 10/9/2018 | 10/9/2018 | P | PASS |
Tom Saunders
|
|
|
We need a wall cover, Jacob is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker... wall cover ok...4 offices and 1 conference rm..conference rm does NOT meet requirement for wall spacing of outlets or floor outlet
|
Issue PAID IN FULL permit | | | 10/8/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/8/2018 | | DONE |
|
|
|
This permit was created on the web by Stacie Tasker
|