Final | 12/20/2018 | 12/21/2018 | 12/20/2018 | A | PASS |
Mark Moncarr
|
|
|
Job is ready for final inspection. Panel schedule is complete on new panel and reworked for existing house panel. Phone #: ###-#### Inspection requested via web by Kurt Carlson Ok final. Looked at on 10/22. This is to close out permit.
|
Permanent Service | 10/22/2018 | 10/23/2018 | 10/23/2018 | A | PASS |
Mark Moncarr
|
|
|
Service was relocated to shop, feeder was then routed underground to the existing house panel. Idaho Power would not allow service on house, due to clearance and non accessibility issues. Existing house panel was turned into a 4 wire sub panel. Existing neutral and grounds were separated and isolated at existing panel. New ground rods installed at new service panel at shop. Main bonding done at new service. I will be on site earlier in the morning and can meet you there if needed. Phone #: ###-#### Inspection requested via web by Kurt Carlson Drop to new service location on detached shop. p/s o/h rec ok
|
Permanent Service | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | CANC |
Mark Moncarr
|
|
|
Idaho power will be on site at 10;30 to shut down, work should be done by 2:00 ready for inspection, Idaho power will turn back on after inspection. Phone #: ###-#### >> Inspection requested via web by Kurt Carlson Inspection cancelled from web by: Kurt Carlson
|
Issue PAID IN FULL permit | | | 10/16/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/16/2018 | | DONE |
|
|
|
This permit was created on the web by Kurt Carlson
|
Telephone call | | | 10/16/2018 | | DONE |
|
|
|
Spoke with Kurt to inform him I corrected the fixture to permanent service instead of misc. work and to speak with Christina about a refund.
|