Final | 12/7/2018 | 12/10/2018 | 12/10/2018 | A | PASS |
Mark Moncarr
|
|
|
Solar system complete and ready for inspection. Approved plans are on site and all work was done according to plans. Call me if you have any questions at 850 8965 Thanks guys Phone #: ###-#### Inspection requested via web by Ryan King Ok final. All labels present. Placard for disconnect location on meter on N side of house.
|
Electrical Rough-In | 11/19/2018 | 11/21/2018 | 11/21/2018 | A | PASS |
Mark Moncarr
|
|
|
listing inspection for solar panels and inverters. The crew will be there from 8am to noon. Thanks guys, Ryan King Phone #: ###-#### Inspection requested via web by Ryan King All components UL listed.
|
Issue PAID IN FULL permit | | | 11/19/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 11/19/2018 | | DONE |
|
|
|
This permit was created on the web by Ryan King
|