Final | 1/3/2019 | 1/3/2019 | 1/3/2019 | P | PASS |
Tom Saunders
|
|
|
Contact: Lynn Vaughn, Please call Lynn before going. Thank you Phone #: ###-#### Inspection requested via web by Deb Gooden... ok to final
|
Final | 12/13/2018 | 12/14/2018 | 12/14/2018 | P | NR |
Tom Saunders
|
|
|
CUSTOMER WILL BE HOME IN THE AFTERNOON TO LET YOU IN HER NAME IS LYNN VAUGHN AND HER NUMBER IS ###-#### Phone #: ###-#### Inspection requested via web by Deb Gooden... not ready for final at this time final needs scheduled once job complete...switch and light installed
|
Electrical Rough-In | 12/14/2018 | 12/14/2018 | 12/14/2018 | P | PASS |
Tom Saunders
|
|
|
CUSTOMER WILL BE HOME IN THE AFTERNOON TO LET YOU IN HER NAME IS LYNN VAUGHN AND HER NUMBER IS ###-#### Phone #: ###-#### Inspection requested via web by Deb Gooden... wiring of new switch and light for new exterior light outside new basement enterance...wired off existing circuit...ok to cover final will need scheduled once switch and light installed
|
Final | 12/13/2018 | 12/14/2018 | 12/13/2018 | A | CANC |
Tom Saunders
|
|
|
Contact: Matt Cinko Phone #: ###-#### >> Inspection requested via web by Deb Gooden Inspection cancelled from web by: Deb Gooden
|
Issue PAID IN FULL permit | | | 12/13/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 12/13/2018 | | DONE |
|
|
|
This permit was created on the web by Deb Gooden
|