Electrical Rough-In | 8/8/2020 | 8/10/2020 | 8/10/2020 | A | CANC |
Mark Moncarr
|
|
|
this inspection is for unit #1, it has a lock box in the back on the door. code 0451. the key inside is for that door. when you go downstairs be careful of the first to second step transition, the framers got the height off and it got me a couple of times Phone #: ###-#### Inspection requested via web by todd cline Called in wrong address.
|
Permanent Service | 12/24/2018 | 12/24/2018 | 12/24/2018 | P | PASS |
Daryl DeGrange
|
|
|
correction complete, p/s o/h rec ok
|
Permanent Service | 12/23/2018 | 12/24/2018 | 12/24/2018 | A | FAIL |
Daryl DeGrange
|
|
|
I would like to get an ok to hook up to Idaho power. we are trying to get this over to Idaho power so they can get the power transfer done by the end of this week. Thanks Todd Phone #: ###-#### Inspection requested via web by todd cline NEC 230.28(A) Service Masts as Supports (A) Strength. The service mast shall be of adequate strength or be supported by braces or guides to withstand safely the strain imposed by the service-drop or overhead conductors. Under sized service mast, Idaho Power overhead service requirements states Use a minimum of 2" conduit for service masts. Masts that penetrate a roof must be rigid steel. EMT or Schedule 80 PVC may be used below a roof. NEC 90.7 Guide kit attached to roof inadequatly installed with sheet metal screws
|
Issue PAID IN FULL permit | | | 12/23/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 12/23/2018 | | DONE |
|
|
|
This permit was created on the web by todd cline
|