Final | 8/30/2019 | 8/30/2019 | 8/30/2019 | P | PASS |
Mark Moncarr
|
|
|
Contact Jesse at ###-####, and we will make sure to have someone to meet you on site. Thanks! Phone #: ###-#### Inspection requested via web by Jesse Simpson Ok final. Line side connection, labels present.
|
Telephone call | | | 6/4/2019 | | DONE |
|
|
|
spoke with Jesse. should have been solar panels for fixture not water feature
|
Electrical Rough-In | 2/4/2019 | 2/4/2019 | 2/4/2019 | P | PASS |
Rock A. Hudson
|
|
|
Roughed in Conduit for future solar project. Conduit is labeled and runs from roof down to pull box near electrical panel. Phone #: ###-#### Inspection requested via web by Jesse Simpson Solar conduit only from roof to boxes next to panel in garage rough in ok cover
|
Issue PAID IN FULL permit | | | 1/9/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 1/9/2019 | | DONE |
|
|
|
This permit was created on the web by Jesse Simpson
|