First Notice | 5/17/2019 | 5/17/2019 | 7/23/2019 | | DONE |
Rock A. Hudson
|
|
|
|
Print Statement | | | 7/23/2019 | | DONE |
|
|
|
|
Final | 5/16/2019 | 5/17/2019 | 5/17/2019 | P | PASS |
Rock A. Hudson
|
|
|
Contact: Dan Schmidt Phone #: ###-#### Inspection requested via web by Deb Gooden No card posted. Final ok
|
Final | 5/15/2019 | 5/16/2019 | 5/16/2019 | A | NR |
Rock A. Hudson
|
|
|
Contact: Dan Schmidt Phone #: ###-#### Inspection requested via web by Deb Gooden Listings confirmed on all, All furniture covers shall be inplace to protect raceways and cables.
|
Final | 5/9/2019 | 5/10/2019 | 5/10/2019 | A | PART |
Rock A. Hudson
|
|
|
Contact: Dan Schmidt Phone #: ###-#### Inspection requested via web by Deb Gooden Need to verify furniture completion. TCO ok
|
Electrical Rough-In | 4/9/2019 | 4/10/2019 | 4/10/2019 | A | PASS |
Rock A. Hudson
|
|
|
CONTACT NAME IS DAN SCHMIDT. CEILING ROUGH IN PLEASE AND THANK YOU Phone #: ###-#### Inspection requested via web by Deb Gooden Grid complete with some decorative luminaires being installed after grid rough in ok cover
|
Electrical Rough-In | 4/2/2019 | 4/3/2019 | 4/3/2019 | P | PASS |
Rock A. Hudson
|
|
|
DAN SCHMIDT ON SITE CONTACT CEILING INSPECTION PLEASE AND THANK YOU Phone #: ###-#### Inspection requested via web by Deb Gooden Reception and production areas not ready, open office area grid rough in ok cover
|
Electrical Rough-In | 2/22/2019 | 2/25/2019 | 2/25/2019 | A | PASS |
Rock A. Hudson
|
|
|
Contact: Dan Schmidt. rough-in for the cafe please Phone #: ###-#### Inspection requested via web by Deb Gooden Cafe walls and drop lids rough in ok cover
|
Electrical Rough-In | 2/19/2019 | 2/20/2019 | 2/20/2019 | P | PART |
Rock A. Hudson
|
|
|
Contact: Dan Schmidt Phone #: ###-#### Inspection requested via web by Deb Gooden Walls except cafe rough in ok cover
|
Issue PAID IN FULL permit | | | 1/21/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 1/21/2019 | | DONE |
|
|
|
This permit was created on the web by Deb Gooden
|