Final | 3/29/2019 | 3/29/2019 | 3/29/2019 | P | PASS |
Mark Moncarr
|
|
|
Final Electrical Inspection - If possible, later in the afternoon would be preferred.
Have a wonderful weekend ; Thank You! Phone #: ###-#### Inspection requested via web by JENNY EMEL Ok final.
|
Permanent Service | 3/7/2019 | 3/8/2019 | 3/8/2019 | A | PASS |
Mark Moncarr
|
|
|
Service Inspection Requested. Contact Keith Chetta @###-#### with questions.
Thank you ; have a nice day! Phone #: ###-#### Inspection requested via web by JENNY EMEL Upper 70a breaker only good for #2 alum. #1 SER has been pulled. Strands may not be cut off to make wire fit in breaker terminals. Will need to see wire reducers installed for 70a breaker upon final. p/s o/h n ok
|
Electrical Rough-In | 2/28/2019 | 3/1/2019 | 3/1/2019 | P | PASS |
Mark Moncarr
|
|
|
Please contact Keith Chetta with any questions
Thank you ; have a lovely day! Phone #: ###-#### Inspection requested via web by JENNY EMEL Ok cover misc lights/switches throughout house.
|
Conference | 2/6/2019 | 2/7/2019 | 2/7/2019 | A | DONE |
Mark Moncarr
|
|
|
Please meet with Keith Chetta on site Thank you Phone #: ###-#### Inspection requested via web by JENNY EMEL Discussed not having to bring kitch counter up to code as there will not be any tile or sheetrock removed. Relocation of outside switch to opposite wall with entry switch.
|
Issue PAID IN FULL permit | | | 2/6/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 2/6/2019 | | DONE |
|
|
|
This permit was created on the web by JENNY EMEL
|