Final | 5/17/2019 | 5/17/2019 | 5/17/2019 | P | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins Final ok
|
Electrical Rough-In | 5/8/2019 | 5/8/2019 | 5/8/2019 | P | PASS |
Rock A. Hudson
|
|
|
Ceiling Inspection Phone #: ###-#### Inspection requested via web by Bryan Atkins Grid rough in ok cover
|
Electrical Rough-In | 3/14/2019 | 3/15/2019 | 3/15/2019 | P | PASS |
Tom Saunders
|
|
|
Walls. Matt ###-#### Phone #: ###-#### Inspection requested via web by Bryan Atkins... wall cover ok
|
Electrical Rough-In | 2/27/2019 | 2/28/2019 | 2/28/2019 | P | PASS |
Tom Saunders
|
|
|
Electrical Floor Box Rough In Phone #: ###-#### Inspection requested via web by Bryan Atkins... 7 floor boxes...ok to cover
|
Issue PAID IN FULL permit | | | 2/27/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 2/27/2019 | | DONE |
|
|
|
This permit was created on the web by Bryan Atkins
|
First Notice | 5/17/2019 | 5/17/2019 | | | |
James Ady
|
|
|
|