Final | 9/6/2019 | 9/9/2019 | 9/9/2019 | A | PASS |
James Ady
|
|
|
informed by contractor they are going to use Tri-State as of 9/4/19. we installed devices on second floor. electrician not onsite. Phone #: ###-#### Inspection requested via web by Matthew White Rough in final only. Project will be completed under ELE19-03371. Final ok
|
Electrical Rough-In | 6/20/2019 | 6/20/2019 | 6/20/2019 | P | PASS |
Mark Moncarr
|
|
|
Info only from office today as damonn is out of area today call office for ###-#### Phone #: ###-#### Inspection requested via web by Matthew White Ok cover upstairs addition.
|
Electrical Rough-In | 6/13/2019 | 6/14/2019 | 6/14/2019 | A | CANC |
Mark Moncarr
|
|
|
electrician not on site, contact Damonn # ###-####. can contact office for details. Phone #: ###-#### Inspection requested via web by Matthew White
|
Permanent Service | 4/25/2019 | 4/25/2019 | 4/25/2019 | P | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Matthew White p/s u/g rec ok
|
Issue PAID IN FULL permit | | | 4/25/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 4/25/2019 | | DONE |
|
|
|
This permit was created on the web by Matthew White
|