Final | 9/17/2019 | 9/17/2019 | 9/17/2019 | P | PASS |
Tom Saunders
|
|
|
Final Inspection Store-it gate code is *053017# Lock code for the cell site is 2019 Main service is in the back of the building on the freeway side. Contact Josh Slater Thank you
Phone #: ###-#### Inspection requested via web by Cathy Duchek..ok to final
|
Final | 7/15/2019 | 7/16/2019 | 7/16/2019 | A | CANC |
Tom Saunders
|
|
|
Store-it gate code is *053017# Lock code for the cell site is 2019. Main service is in the back of the building on the freeway side. Contact Josh Slater Phone #: ###-#### Inspection requested via web by Cathy Duchek... unable to final...power must be on before permit can be finaled
|
Rough-In Permanent Service | 7/16/2019 | 7/16/2019 | 7/16/2019 | A | PASS |
Tom Saunders
|
|
|
Store-it gate code is *053017# Lock code for the cell site is 2019. Main service is in the back of the building on the freeway side. Contact Josh Slater Phone #: ###-#### Inspection requested via web by Cathy Duchek... rough ok p/s u/g new ok...1 meter 3 blanks for meter pac
|
Final | 7/15/2019 | 7/15/2019 | 7/15/2019 | P | FAIL |
Tom Saunders
|
|
|
Final Inspection for Cell Site Contact electrician Josh Slater Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek.. no access and no answer on contact phone number...left message requiring rough inspection...contractor required to be present at time of inspection
|
Electrical Rough-In | 5/20/2019 | 5/21/2019 | 5/21/2019 | P | PASS |
Rock A. Hudson
|
|
|
Underground Inspection at cell site Contact Alex Ybarra Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Underground from service to west and south rough in ok cover
|
Issue PAID IN FULL permit | | | 5/20/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/20/2019 | | DONE |
|
|
|
This permit was created on the web by Cathy Duchek
|
First Notice | 9/17/2019 | 9/17/2019 | | | |
Tom Saunders
|
|
|
|