Final | 7/2/2019 | 7/3/2019 | 7/3/2019 | A | PASS |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by mark hood Ok final.
|
Final | 6/3/2019 | 6/4/2019 | 6/4/2019 | P | CANC |
Tom Saunders
|
|
|
Need inspection for Idaho Power reconnect. Early afternoon if possible. Thanks Phone #: ###-#### Inspection requested via web by mark hood... needed perm service...will schedule final once service meter installed
|
Permanent Service | 6/4/2019 | 6/4/2019 | 6/4/2019 | P | PASS |
Tom Saunders
|
|
|
Need inspection for Idaho Power reconnect. Early afternoon if possible. Thanks Phone #: ###-#### Inspection requested via web by mark hood... p/s u/g reconnect ok
|
Issue PAID IN FULL permit | | | 6/3/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/3/2019 | | DONE |
|
|
|
This permit was created on the web by mark hood
|