Final | 1/29/2020 | 1/30/2020 | 1/30/2020 | P | PASS |
James Ady
|
|
|
Rich Phone #: ###-#### corrections made final ok
|
Final | 1/22/2020 | 1/23/2020 | 1/23/2020 | P | FAIL |
James Ady
|
|
|
richard Phone #: ###-#### Laundry room counter recep dead, 2 pole Lock out needed for Water heater breaker
|
Electrical Rough-In | 7/15/2019 | 7/16/2019 | 7/17/2019 | P | PASS |
James Ady
|
|
|
Rich Phone #: ###-#### Rough in of M. Bed, M. Bath, Laundry room and geust bed ok to cover
|
Electrical Rough-In | 7/11/2019 | 7/15/2019 | 7/15/2019 | A | FAIL |
James Ady
|
|
|
Rich Phone #: ###-#### Finish make up(Pigtail receps and switches, finish all attic j-boxes) Swap dryer box with listed 2gang box. Move all staples to outside of 1 1/4in from face of stud. Install smoke detectors per code.
|
Conference | 6/17/2019 | 6/19/2019 | 6/19/2019 | A | PASS |
James Ady
|
|
|
Rich Phone #: ###-#### Customer adding Master bed, bath and closet as well as 1 bed and a laundry room. Discussed 20A for laundry, 20A for Bath vanity, 30A for dryer, AFCI for beds, Tamper resistant receps for all locations. Adding Furnace in crawl. Will require Light and recep, both will need GFCI protection.
|
Application received | | | 6/17/2019 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/17/2019 | | DONE |
|
|
|
|