Final | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | PASS |
Mark Moncarr
|
|
|
Doors will be unlocked any questions please give me a call thank you Phone #: ###-#### Inspection requested via web by David Kubik Ok final.
|
Permanent Service | 7/1/2019 | 7/1/2019 | 7/1/2019 | P | PASS |
Mark Moncarr
|
|
|
p/s o/h n ok
|
Electrical Rough-In | 7/1/2019 | 7/1/2019 | 7/1/2019 | A | PASS |
Mark Moncarr
|
|
|
House will be open. Inspection is for both down stairs unit and service. Any questions please let me know. Thank you. Phone #: ###-#### Inspection requested via web by David Kubik Ok cover main level. Need a 3way switch added to bottom of stairs for basement by final.
|
Fees Due Hold | 6/27/2019 | | 7/1/2019 | | DONE |
|
|
|
|
Miscellaneous action | | | 6/26/2019 | | DONE |
|
|
|
called and talked to Daryl D and he said the fee would be 110.00 because there are 1 serv over 200 AMP and 30 new branch circuits
|
Electrical Rough-In | 6/23/2019 | 6/24/2019 | 6/24/2019 | A | PASS |
Mark Moncarr
|
|
|
give me a call when you get there just in case it''s not unlocked I''ll give you the code and I have a couple questions for you on the permit pricing. This would be just to inspect the upstairs unit Phone #: ###-#### Inspection requested via web by David Kubik Ok cover upstairs unit 3.
|
Issue PAID IN FULL permit | | | 6/23/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/23/2019 | | DONE |
|
|
|
This permit was created on the web by David Kubik
|
First Notice | 10/15/2019 | 10/15/2019 | | | |
Mark Moncarr
|
|
|
|