First Notice | 1/31/2020 | 1/31/2020 | 4/30/2020 | | DONE |
Daryl DeGrange
|
|
|
This permit finaled on the web by Tom Jenkins
|
Final | 1/31/2020 | 1/31/2020 | 1/31/2020 | P | PASS |
Daryl DeGrange
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins job complete, final ok
|
Conference | 12/11/2019 | 12/11/2019 | 12/11/2019 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins...discussed requirement for grounding and bonding of new service multi pac being added to existing concrete building
|
Electrical Rough-In | 11/21/2019 | 11/21/2019 | 11/21/2019 | P | CANC |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins..wiil reschedule...issue with hitting gas line
|
Electrical Rough-In | 7/15/2019 | 7/16/2019 | 7/16/2019 | A | PASS |
Eric Story
|
|
|
We need a uffer inspection for building 1. Thank you Phone #: ###-#### Inspection requested via web by Tom Jenkins Uffer for building 1 with #4 copper installed ok to cover. Eplan states 2/0 to be installed this is not main switch gear on this building as just a branch feed to openers and lights to be installed
|
Issue PAID IN FULL permit | | | 6/24/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/24/2019 | | DONE |
|
|
|
This permit was created on the web by Tom Jenkins
|