Final | 7/9/2019 | 7/9/2019 | 7/9/2019 | P | PASS |
Eric Story
|
|
|
Final for Solar Array install ok
|
Final | 7/8/2019 | 7/8/2019 | 7/8/2019 | P | PASS |
Eric Story
|
|
|
We can meet you onsite to walk you through the system. Phone #: ###-#### Inspection requested via web by Jesse Simpson Final ok
|
Electrical Rough-In | 7/5/2019 | 7/8/2019 | 7/8/2019 | A | PASS |
Eric Story
|
|
|
Will be on site with solar panels and other equipment Phone #: ###-#### Inspection requested via web by Jesse Simpson Will need approved plans onsite for final inspection Verified U/L listing and scope of work for Solar Array install
|
Application received | | | 6/25/2019 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/25/2019 | | DONE |
|
|
|
|