Final | 8/8/2019 | 8/8/2019 | 8/8/2019 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Virginia Jesop... Labelling, disconnect, and OCPD ok fuses with line side connection
|
Rough-In Permanent Service | 8/5/2019 | 8/8/2019 | 8/8/2019 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Virginia Jesop... UL listed equipment
|
Final | 7/18/2019 | 7/22/2019 | 7/22/2019 | A | CANC |
Tom Saunders
|
|
|
Brittany Phone #: ###-####... Boise city ordinance requires a rough inspection of solar install before a final can be given job is complete...panels need removed and brought to ground level for inspection of listing and labelling...licensed electrician required to be on sight for inspection...spoke with Virginia solar rep and made aware of requirements 7/22/19 at 10AM
|
Issue PAID IN FULL permit | | | 7/10/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/10/2019 | | DONE |
|
|
|
This permit was created on the web by Virginia Jesop
|