First Notice | 9/18/2019 | 9/18/2019 | 5/15/2020 | | DONE |
Rock A. Hudson
|
|
|
This permit finaled on the web by Deb Gooden
|
Final | 9/18/2019 | 9/18/2019 | 9/18/2019 | P | PASS |
Rock A. Hudson
|
|
|
Contact: Mike Mulvahill Phone #: ###-#### Inspection requested via web by Deb Gooden Final ok
|
Electrical Rough-In | 9/11/2019 | 9/11/2019 | 9/11/2019 | P | PASS |
Eric Story
|
|
|
CONTACT: MIKE MULVAHILL - ceiling inspection please Phone #: ###-#### Inspection requested via web by Deb Gooden Ceiling only ok to cover
|
Permanent Service | 9/10/2019 | 9/11/2019 | 9/11/2019 | P | PASS |
Eric Story
|
|
|
Contact: Mike Mulvahill Phone #: ###-#### Inspection requested via web by Deb Gooden p/s u/g n ok 1meter needed
|
Electrical Rough-In | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | PASS |
Rock A. Hudson
|
|
|
CONTACT: MIKE MULVAHILL Phone #: ###-#### Inspection requested via web by Deb Gooden Walls and hardlids rough in ok cover
|
Issue PAID IN FULL permit | | | 7/25/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/25/2019 | | DONE |
|
|
|
This permit was created on the web by Deb Gooden
|