Final | 8/14/2019 | 8/14/2019 | 8/14/2019 | P | PASS |
Eric Story
|
|
|
Verified with contractor rough-in specifications on solar install and scope of work. All components all U/L listed will final out permit as needed Final ok
|
Final | 8/13/2019 | 8/14/2019 | 8/14/2019 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Seth Stears Final ok
|
Change Status to I | | | 8/14/2019 | | DONE |
|
|
|
Per Eric S, didnt mean to final permit yet
|
Issue PAID IN FULL permit | | | 7/30/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/30/2019 | | DONE |
|
|
|
This permit was created on the web by Seth Stears
|