Electrical Rough-In | 9/24/2019 | 9/24/2019 | 9/24/2019 | A | PASS |
Mark Moncarr
|
|
|
Please call or text when on your way. Phone #: ###-#### Inspection requested via web by Josh Reeder Ok final. Corrections made
|
Electrical Rough-In | 9/22/2019 | 9/23/2019 | 9/23/2019 | A | FAIL |
Mark Moncarr
|
|
|
Text or call please when you are on the way. Phone #: ###-#### Inspection requested via web by Josh Reeder 1.Stapling needed above boxes. 2. 20a circuit needed for bathrooms and laundry. 3. All grounds and neutrals need made up in all boxes. 4. Some boxes need replaced to a larger size to allow for box fill.
|
Electrical Rough-In | 9/23/2019 | 9/23/2019 | 9/23/2019 | A | CANC |
Mark Moncarr
|
|
|
Text or call please when you are on the way. Phone #: ###-#### >> Inspection requested via web by Josh Reeder Inspection cancelled from web by: Josh Reeder
|
Conference | 8/22/2019 | 8/23/2019 | 8/22/2019 | A | DONE |
Mark Moncarr
|
|
|
Check exterior Phone #: ###-#### Inspection requested via web by Josh Reeder Met with Josh on 8/22/19 to discuss service location. Existing service to be replaced with new in same location. There are 2 windows, 1 on each side of overhead mast. 230.9(A) Ex. states that conductors that are run above top of window shall be permitted to be less than 3ft. Both windows do not open in upward motion. They both open in like 2 doors. With windows open, you could reach conductors.
|
Conference | 8/7/2019 | 8/8/2019 | 8/8/2019 | A | DONE |
Mark Moncarr
|
|
|
Call to meet // Josh Phone #: ###-#### Discussed outlet layout and the requirement for dedicated circuits, ex. kitchen, baths etc. Also discussed service requirements.
|
Issue PAID IN FULL permit | | | 8/7/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/7/2019 | | DONE |
|
|
|
This permit was created on the web by Josh Reeder
|