Electrical Rough-In | 10/29/2019 | 10/29/2019 | 10/29/2019 | P | PASS |
Eric Story
|
|
|
Available after 3pm. Follow up to previous rough-in; landed conductors on panel and fixed disposal switch. Phone #: ###-#### Inspection requested via web by Kyle Haugland Panel wall ok to cover
|
Electrical Rough-In | 10/24/2019 | 10/25/2019 | 10/25/2019 | P | PASS |
Eric Story
|
|
|
Rough in of new kitchen circuits has been completed and need inspection to verify proper installation before drywall is installed. Phone #: ###-#### Inspection requested via web by Kyle Haugland Kitchen roug in ok to cover Owner will call another rough-in for when panel gets landed
|
Permanent Service | 9/30/2019 | 10/1/2019 | 10/1/2019 | P | PASS |
Eric Story
|
|
|
Installed new service entrance, meter socket, and panel for 200 amp service. I will be at least 30 minutes away, but if I know in advance I can plan on meeting you at the house at the appropriate time. Phone #: ###-#### Inspection requested via web by Kyle Haugland p/s o/h rec ok
|
Conference | 9/5/2019 | 9/6/2019 | 9/6/2019 | P | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Haugland Discussed service change and kitchen remodel. Owner has done all research to complete the job and is knowledgeable.
|
Application received | | | 9/5/2019 | | DONE |
|
|
|
This permit was created on the web by Kyle Haugland
|
Issue PAID IN FULL permit | | | 9/5/2019 | | DONE |
|
|
|
|