Electrical Rough-In | 9/22/2019 | 9/23/2019 | 9/23/2019 | A | PASS |
Mark Moncarr
|
|
|
equipotential plane, potting of pool lights, and bonding volleyball anchors for new pool construction Phone #: ###-#### Inspection requested via web by Jordan Camie Volleyball pockets, eq plane and potting ok cover
|
Electrical Rough-In | 9/17/2019 | 9/18/2019 | 9/18/2019 | P | PASS |
Mark Moncarr
|
|
|
Underground inspection for new pool construction Phone #: ###-#### Inspection requested via web by Jordan Camie Ok cover grd work for 1 light and 1 going to motor location.
|
Electrical Rough-In | 9/10/2019 | 9/11/2019 | 9/11/2019 | A | PASS |
Eric Story
|
|
|
bonding inspection for new pool (rebar) Call Jordan with any questions 2088912289 Phone #: ###-#### Inspection requested via web by Jordan Camie Pool bonding on all 4 corners and 1 light ok to cover
|
Issue PAID IN FULL permit | | | 9/10/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/10/2019 | | DONE |
|
|
|
This permit was created on the web by Jordan Camie
|