Final | 6/9/2020 | 6/10/2020 | 6/10/2020 | A | PASS |
Mark Moncarr
|
|
|
Key lock at front door, LOL will unlock to access key. Phone #: ###-#### Inspection requested via web by Ryan Wilson Max fuse 20, 20a brkr installed.
|
Final | 6/9/2020 | 6/9/2020 | 6/9/2020 | P | FAIL |
Mark Moncarr
|
|
|
No access, home not occupied. Requested picture of brkr size by 6/5, never received. Texted contractor on morning of 6/8 about 730 and asked if pictures were available, response was I would receive picture on 6/9, never received. I will no longer accept pictures from contractor. From here on out , ALL inspections will require coordinated access in order to be finaled.
|
Change Status to I | | | 6/9/2020 | | DONE |
|
|
|
reopen per Mark
|
Final | 6/2/2020 | 6/3/2020 | 6/3/2020 | A | PASS |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Wilson Ok final. 20a max, 20a installed
|
Issue PAID IN FULL permit | | | 9/11/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/11/2019 | | DONE |
|
|
|
This permit was created on the web by Ryan Wilson
|