Final | 2/5/2020 | 2/6/2020 | 2/6/2020 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Tyler Ridley...ok to final
|
Permanent Service | 1/29/2020 | 1/30/2020 | 1/30/2020 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Tyler Ridley...p/s o/h reconnect ok
|
Telephone call | | | 1/30/2020 | | DONE |
|
|
|
per Tyler, adding up to 200A electrical panel. Added fees, fixture and paid GDB
|
Final | 1/15/2020 | 1/16/2020 | 1/16/2020 | A | PEND |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Tyler Ridley... bsmt wiring ok...requiring contractor do a load calculation on outside panel where new wiring comes from...100A main breaker overloaded and busing rated for 125A max
|
Electrical Rough-In | 11/6/2019 | 11/7/2019 | 11/7/2019 | A | PASS |
Eric Story
|
|
|
Basement rough in inspection Phone #: ###-#### Inspection requested via web by Tyler Ridley Basement ok to cover
|
Issue PAID IN FULL permit | | | 9/24/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/24/2019 | | DONE |
|
|
|
This permit was created on the web by Tyler Ridley
|