Electrical Rough-In | 7/23/2020 | 7/23/2020 | 7/23/2020 | A | PASS |
Eric Story
|
|
|
1st and 2nd floor ceiling drops Phone #: ###-#### Inspection requested via web by Todd Hall 1st and 2nd floor drop ceilings ok to cover
|
Electrical Rough-In | 7/13/2020 | 7/14/2020 | 7/14/2020 | A | PASS |
Rock A. Hudson
|
|
|
3rd and 4th floor ceiling drops Phone #: ###-#### Inspection requested via web by Todd Hall Areas noted, sticker on north west window, rough in ok cover
|
Rough-In Permanent Service | 6/10/2020 | 6/11/2020 | 6/11/2020 | A | PASS |
Tom Saunders
|
|
|
rough in complete: Units, Shaft liners, Breezeways, Heat cable circuits Phone #: ###-#### Inspection requested via web by Todd Hall... rough ok to cover check heat tape junction box access at final p/s u/g new ok...17 meters needed
|
Electrical Rough-In | 5/20/2020 | 5/21/2020 | 5/21/2020 | A | PASS |
Tom Saunders
|
|
|
rough in for 1st, 2nd and 3rd floor (12 units). Phone #: ###-#### Inspection requested via web by Todd Hall...shear wall ok to cover-12 units so can set bath tub
|
Telephone call | | | 2/19/2020 | | DONE |
|
|
|
Adding Building information to scope of work. per janell at trax electric
|
Issue PAID IN FULL permit | | | 10/23/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/23/2019 | | DONE |
|
|
|
This permit was created on the web by Todd Hall
|