Electrical Rough-In | 1/15/2020 | 1/16/2020 | 1/16/2020 | P | PASS |
Rock A. Hudson
|
|
|
after 3pm // Matthew Phone #: ###-#### Will need to confirm cooktop and oven boxes of sufficient size. will verify on final. Kitchen rough in ok cover
|
Electrical Rough-In | 12/10/2019 | 12/10/2019 | 12/10/2019 | P | PASS |
Eric Story
|
|
|
Matt Phone #: ###-#### Kitchen back stove wall ok to cover, Will need to see correct size wire for oven installed proir to cabinet being installed
|
Conference | 11/29/2019 | 12/2/2019 | 12/2/2019 | P | DONE |
Eric Story
|
|
|
Mathew Phone #: ###-#### Discuused wiring of kitchen remodel- receptacle layout and required branch circuit needed.
|
Application received | | | 11/29/2019 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/29/2019 | | DONE |
|
|
|
|