Final | 2/26/2020 | 2/27/2020 | 2/27/2020 | A | PASS |
Mark Moncarr
|
|
|
Ok final.
|
Final | 2/25/2020 | 2/26/2020 | 2/26/2020 | A | CANC |
Mark Moncarr
|
|
|
Cover inspection for grid ceiling and final inspection for the entire project. Phone #: ###-#### Inspection requested via web by Steve Craig Talked to contractor, rescheduled for 2/27
|
Electrical Rough-In | 1/8/2020 | 1/8/2020 | 1/8/2020 | P | PASS |
Mark Moncarr
|
|
|
Rough in cover of walls. Phone #: ###-#### Inspection requested via web by Steve Craig Ok cover walls and grd work for 2 floor box location.
|
Issue PAID IN FULL permit | | | 1/8/2020 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 1/8/2020 | | DONE |
|
|
|
This permit was created on the web by Steve Craig
|
First Notice | 2/27/2020 | 2/27/2020 | | | |
Mark Moncarr
|
|
|
|