Final | 5/27/2020 | 5/28/2020 | 5/28/2020 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Sherry Allen...scope of work complete...mounting of equipment and grounding of future service done...no request for energization...ok to final
|
Rough-In Permanent Service | 1/21/2020 | 1/22/2020 | 1/22/2020 | A | PASS |
Tom Saunders
|
|
|
This is for a service inspection. Access it from inside the apartment parking lot. Phone #: ###-#### Inspection requested via web by Sherry Allen...p/s u/g new ok
|
Issue PAID IN FULL permit | | | 1/15/2020 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 1/15/2020 | | DONE |
|
|
|
This permit was created on the web by Sherry Allen
|
First Notice | 5/28/2020 | 5/28/2020 | | | |
Tom Saunders
|
|
|
|