Final | 4/28/2020 | 4/28/2020 | 4/28/2020 | P | PASS |
Tom Saunders
|
|
|
Hedi Please call***Try Video** Phone #: ###-####...ok to final
|
Electrical Rough-In | 4/13/2020 | 4/13/2020 | 4/13/2020 | P | PASS |
Tom Saunders
|
|
|
virtual inspeciton requested // Heidi Phone #: ###-####... rough ok to cover...pictures sent per covid19 requirement...2 gang junction box will be replaced and verified at final
|
Conference | 3/23/2020 | 3/24/2020 | 3/24/2020 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Heidi Lema...discussed wiring of newly created bedroom and bathroom...AFCI requirements and dedicated 20A circuit for bath...pamphlet given...let known required to get building permit and a mechanical permit as well...homeowner competent in work
|
Issue PAID IN FULL permit | | | 3/21/2020 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/21/2020 | | DONE |
|
|
|
This permit was created on the web by Heidi Lema
|