Final | 6/17/2020 | 6/18/2020 | 6/18/2020 | P | PASS |
James Ady
|
|
|
will be open Phone #: ###-#### Inspection requested via web by Darryn Coburn Corrections made Final ok
|
Final | 6/16/2020 | 6/17/2020 | 6/17/2020 | P | PART |
James Ady
|
|
|
Will be open, call Jerry with any questions ###-#### Phone #: ###-#### Inspection requested via web by Darryn Coburn Panel EP1 mislabeled, Redundent GFCI EP3 31 GFCI above small sink in coke room, Downsize breaker for small water heater above restrooms 2 pole 30 installed needs 2 pole 20. Partial final only ok
|
Electrical Rough-In | 6/10/2020 | 6/11/2020 | 6/11/2020 | P | PASS |
James Ady
|
|
|
This request is for a ceiling grid inspection please. Phone #: ###-#### Inspection requested via web by Darryn Coburn Ceiling only ok to cover
|
Electrical Rough-In | 5/7/2020 | 5/8/2020 | 5/8/2020 | P | PASS |
James Ady
|
|
|
this request is for wall and bathroom ceiling inspection. Phone #: ###-#### Inspection requested via web by Darryn Coburn Walls throughout and Restroom hard lids ok to cover
|
Electrical Rough-In | 3/30/2020 | 3/30/2020 | 3/30/2020 | P | PASS |
Rock A. Hudson
|
|
|
This request is for an underground inspection. Please call Jerry with any questions ###-####, thank you! Phone #: ###-#### Inspection requested via web by Darryn Coburn City approved set of plans on site confirmed. Underslab rough in ok cover
|
Issue PAID IN FULL permit | | | 3/30/2020 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 3/30/2020 | | |
|
|
|
|
Application received | | | 3/30/2020 | | DONE |
|
|
|
This permit was created on the web by Darryn Coburn
|
First Notice | 6/18/2020 | 6/18/2020 | | | |
James Ady
|
|
|
|