Final | 7/23/2020 | 7/24/2020 | 7/24/2020 | A | PASS |
James Ady
|
|
|
Justin is our contact. He has made arrangements for virtual inspection with inspector due to activity at job site. Thank you Phone #: ###-#### Inspection requested via web by Kelly Felin final ok
|
Electrical Rough-In | 7/24/2020 | 7/24/2020 | 7/24/2020 | P | PASS |
James Ady
|
|
|
Justin is our contact. He has made arrangements for virtual inspection with inspector due to activity at job site. Thank you Phone #: ###-#### Inspection requested via web by Kelly Felin Sub panel and electric heater rough in ok.
|
Final | 7/23/2020 | 7/23/2020 | 7/23/2020 | P | NR |
James Ady
|
|
|
Justin is our contact at ###-#### Phone #: ###-#### Inspection requested via web by Kelly Felin not ready
|
Issue PAID IN FULL permit | | | 7/23/2020 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/23/2020 | | DONE |
|
|
|
This permit was created on the web by Kelly Felin
|