Site Final | 3/8/2007 | 3/8/2007 | 3/8/2007 | P | PASS |
Steven Webb
|
|
|
|
DOC - Permit Finaled | 9/26/2005 | 9/26/2005 | 9/26/2005 | P | PASS |
Aimee Hughes
|
|
|
|
Conference | 9/13/2004 | 9/13/2004 | 9/13/2004 | A | PART |
Aimee Hughes
|
|
|
Steve and I met with GC (Carl) and Mike with Public Works to walk the site and discuss any concerns or questions regarding pumping and discharge. The site looks okay and has been documented with pictures at 9:30 on 9/13/04.
|
Site Preparation | 5/14/2004 | 5/14/2004 | 5/14/2004 | P | PART |
Steven Webb
|
|
|
|
Site Preparation | 3/8/2004 | 3/8/2004 | 3/8/2004 | A | PASS |
Steven Webb
|
|
|
|
Site Preparation | 12/31/2003 | 12/31/2003 | 12/31/2003 | A | PASS |
Steven Webb
|
|
|
|
Issue & PRINT permit COM | | | 12/8/2003 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 12/2/2003 | | 12/2/2003 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 11/26/2003 | | 11/26/2003 | | FAIL |
|
|
|
Information to be included on ESC plan:
1. Listed BMP drawings to be included in plan
2. Discussion of Oil spill measures to be included
3. Discussion of EPA NOI requirements
4. Include a copy of EPA Const. Site SWPPP check list
5. Include a copy of Storm Water Construction General Permit Requirements
Contacted Plan Designer on 11/26/03
|
Routing - Erosion and Sediment | 9/25/2003 | | 9/25/2003 | | FAIL |
|
|
|
No ESC narrative attached to plans.
|
Application received | | | 9/15/2003 | | |
|
|
|
|