Site Final | 7/8/2008 | 7/8/2008 | 7/8/2008 | P | PASS |
Clint A Smith
|
|
|
All work has been complete with this project. CAS
|
Tracking Control | 1/26/2005 | 1/28/2005 | 1/28/2005 | A | PASS |
Aimee Hughes
|
|
|
issues on c/n have been addressed. construction entrance has been repaired, d/i 's have been repaired. sweeper is scheduled for weekly clean up. met with RP (Bruce). will follow up. 1/28/2005 8:52:57 AM 1/28/2005 8:54:20 AM
|
Tracking Control | 1/25/2005 | 1/26/2005 | 1/26/2005 | A | FAIL |
Steven Webb
|
|
|
Correction notice issued, complete by the end of the day 1/27/05 or a stop work can be issued. 1/26/2005 12:49:24 PM
|
Tracking Control | 1/25/2005 | 1/25/2005 | 1/25/2005 | P | FAIL |
Steven Webb
|
|
|
Tracking from job site--RP Bruce-###-####: Anna ###-#### CM. Will get sweeper. 1/25/2005 4:06:56 PM
|
Tracking Control | 11/29/2004 | 11/29/2004 | 11/29/2004 | P | PART |
Aimee Hughes
|
|
|
track out is being maintained as well as construction entrance. 11/29/2004 1:23:22 PM
|
Tracking Control | 10/21/2004 | 10/21/2004 | 10/21/2004 | P | FAIL |
Steven Webb
|
|
|
Excessive track out onto Mcmillian, correction to rp--sweep as needed. Will follow up. 10/21/2004 1:02:00 PM
|
Issue & PRINT permit COM | | | 8/24/2004 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 8/10/2004 | | 8/10/2004 | | PASS |
|
|
|
ESC approved with attached conditions.
|
Routing - Erosion and Sediment | 6/15/2004 | | 6/15/2004 | | FAIL |
|
|
|
Contractor is listed as CM company. Individual listed as RP not certified by Boise City.
|
Application received | | | 5/28/2004 | | |
|
|
|
|