Aging Inspection | 3/2/2011 | 3/2/2011 | 3/2/2011 | | CANC |
Daryl DeGrange
|
|
|
|
Site Final | 3/2/2011 | 3/2/2011 | 3/2/2011 | A | PASS |
Daryl DeGrange
|
|
|
job site clean, landscape is in, construction is finished final ok
|
Site Preparation | 3/2/2011 | 3/2/2011 | 3/2/2011 | A | CANC |
Daryl DeGrange
|
|
|
|
Aging Inspection | 12/31/2010 | 12/31/2010 | 1/3/2011 | | CANC |
Steven Webb
|
|
|
HOLIDAY
|
(F) Reprint permit | | | 10/3/2005 | | DONE |
|
|
|
|
(F) Reprint permit | | | 5/9/2005 | | DONE |
|
|
|
|
Site Preparation | 4/15/2005 | 4/19/2005 | 4/19/2005 | A | PASS |
Aimee Hughes
|
|
|
site looks okay. contacted RP about maintaining BMP's
|
Site Preparation | 4/15/2005 | 4/15/2005 | 4/15/2005 | P | PART |
Steven Webb
|
|
|
Contractor submitted RP information to Boise City. Follow plan and permit conditions. Will follow up.
|
Site Preparation | 4/15/2005 | 4/15/2005 | 4/15/2005 | P | FAIL |
Steven Webb
|
|
|
Per esc conditions, no 48 Hour notice was given to Boise City, also, no rp is listed under permit. Provide the rp information to Boise City by the end of today or further enforcement will occur.
|
Issue & PRINT permit SFD | | | 3/17/2005 | | DONE |
|
|
|
|
Telephone call | | | 2/9/2005 | | DONE |
|
|
|
talked kevin mccarthy ###-#### said the owner is having health issues and will let him know permit is still here
|
Telephone call | | | 12/16/2004 | | DONE |
|
|
|
talked to kevin mccarthy (###-####)said owner has been in hospital but will still pickup soon
|
Permit Ready to Issue | | | 10/8/2004 | | DONE |
|
|
|
|
Telephone call | | | 10/8/2004 | | DONE |
|
|
|
Spoke with Kevin and told him that permit is ready & fees///8:05am 10/08/04 BAS
|
Application received | | | 10/7/2004 | | |
|
|
|
|
Routing - Erosion and Sediment | 10/7/2004 | | 10/7/2004 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/7/2004 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 10/7/2004 | | | | PEND |
|
|
|
|