Site Final | 12/27/2006 | 12/27/2006 | 12/27/2006 | P | PASS |
Aimee Hughes
|
|
|
|
Random Inspection | 12/14/2005 | 12/14/2005 | 12/14/2005 | P | PASS |
Aimee Hughes
|
|
|
Site looks good.
|
Random Inspection | 11/22/2005 | 11/22/2005 | 11/22/2005 | P | PASS |
Aimee Hughes
|
|
|
Site looks good. Met with RP to inspect to approved ESC plans.
|
Random Inspection | 7/1/2005 | 7/1/2005 | 7/1/2005 | P | PASS |
Aimee Hughes
|
|
|
site looks good, all bmp's are being maintained.
|
Issue & PRINT permit SFD | | | 5/31/2005 | | |
|
|
|
|
Site Preparation | 5/24/2005 | 5/24/2005 | 5/24/2005 | P | PASS |
Aimee Hughes
|
|
|
stopped by to look at bmp installation.
|
Random Inspection | 5/23/2005 | 5/23/2005 | 5/23/2005 | P | PASS |
Steven Webb
|
|
|
Bark wattles in place, reseeding has been done over new stormdrain. Bark mulch over seeded area.
|
Issue & PRINT permit SFD | | | 5/4/2005 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 4/6/2005 | | 4/6/2005 | | PASS |
|
|
|
ESC resubmittal approved with attached conditions.
|
Routing - Erosion and Sediment | 3/31/2005 | | 3/31/2005 | | FAIL |
|
|
|
ESC does not meet standards set forth in BCC 8-17, also not mention of adding strom drain through property.
|
Routing - Erosion and Sediment | 3/15/2005 | | 3/15/2005 | | DONE |
|
|
|
Discussed with contractor--ACHD will be adding land disturbance outside of what is listed in original plan. Requested contractor submit addendum to outline this change.
|
Routing - Erosion and Sediment | 3/11/2005 | | 3/11/2005 | | FAIL |
|
|
|
ESC plan failed, no ESC application with plans. Contacted PD.
|
Application received | | | 2/25/2005 | | |
|
|
|
|