Site Final | 5/13/2010 | 5/18/2010 | 5/18/2010 | A | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 5/18/2010 | 5/18/2010 | 5/18/2010 | P | PASS |
Dave Hannah
|
|
|
|
Random Inspection | 11/7/2005 | 11/7/2005 | 11/7/2005 | P | PART |
Steven Webb
|
|
|
Drop inlet bag needs attention, signage is not visable, concrete washout area is needed and continue to maintain construction entrance. Sweep daily or as needed.
|
Conference | 10/10/2005 | 10/11/2005 | 10/11/2005 | A | DONE |
Steven Webb
|
|
|
Conf. with rp to reveiw esc plan at job site. Reviewed bmp' and esc plan with rp and contractor. Everything looks good. RP-Darrell ###-####; Contractor Ed R. ###-####. Contact either one regarding problems.
|
Conference | 10/10/2005 | 10/10/2005 | 10/10/2005 | P | DONE |
Steven Webb
|
|
|
Received 48 hour notice to start construction.
|
Issue & PRINT permit COM | | | 10/7/2005 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 10/5/2005 | | 10/5/2005 | | PASS |
|
|
|
ESC plan modification approved with attached conditions. Plan modification was needed due to the soils (17,000 cubic yards) stockpile location was changed to a pit to Trappers Island.
|
Routing - Erosion and Sediment | 5/11/2005 | | 5/11/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - Erosion and Sediment | 5/9/2005 | | 5/9/2005 | | DONE |
|
|
|
Received rp information via fax from Tamura. Still need to submit esc plan which meets 8-17.
|
Routing - Erosion and Sediment | 5/5/2005 | | 5/5/2005 | | FAIL |
|
|
|
ESC plan does not meet conditions set forth in BMC 8-17. Informed PD. Checklist completed. ALSO; contractor is called out under BLD number so RP name and number is required. Informed Tamura via voice mail.
|
Application received | | | 4/7/2005 | | |
|
|
|
|