Site Final | 9/30/2009 | 9/30/2009 | 9/30/2009 | P | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 9/30/2009 | 9/30/2009 | 9/30/2009 | P | PASS |
Dave Hannah
|
|
|
|
Tracking Control | 11/3/2005 | 11/17/2005 | 11/18/2005 | A | PASS |
Aimee Hughes
|
|
|
Site looks okay.
|
Site Preparation | 10/31/2005 | 11/1/2005 | 11/3/2005 | A | PASS |
Aimee Hughes
|
|
|
Received 48 hr. notice. Construction just getting underway. bmp's are being installed.
|
Site Preparation | 10/7/2005 | 10/28/2005 | 10/31/2005 | A | CANC |
Aimee Hughes
|
|
|
|
Issue & PRINT permit SFD | | | 10/12/2005 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 10/11/2005 | | 10/11/2005 | | PASS |
|
|
|
ESC plan resubmittal approved with attached conditions.
|
Site Preparation | 9/29/2005 | 10/6/2005 | 10/7/2005 | A | CANC |
Aimee Hughes
|
|
|
|
Site Preparation | 9/16/2005 | 9/27/2005 | 9/29/2005 | A | CANC |
Aimee Hughes
|
|
|
Construction has not started.
|
Routing - Erosion and Sediment | 9/14/2005 | | 9/14/2005 | | FAIL |
|
|
|
ESC plan does not meet requirments per BMC 8-17; notified PD. Checklist completed and faxed to PD.
|
Application received | | | 9/2/2005 | | |
|
|
|
|