Site Final | 7/31/2008 | 7/31/2008 | 7/31/2008 | A | PASS |
Tom Arcoraci
|
|
|
|
Site Final | 7/28/2008 | 7/28/2008 | 7/28/2008 | A | CANC |
Tom Arcoraci
|
|
|
|
Site Final | 7/28/2008 | 7/28/2008 | 7/28/2008 | A | CANC |
Tom Arcoraci
|
|
|
|
Complaint Inspection | 3/28/2008 | 3/28/2008 | 3/28/2008 | A | PART |
Clint A Smith
|
|
|
Discussed with RP over track out onto Eldorado st. Gave him till the end of the day to get tracking cleaned up. Also to re-install construction entrance to the CGP standards. Prior to leaving they had a street sweeper com through. Recommended perimeter access control on project to eliminate track out of project. CAS #460
|
Complaint Inspection | 12/17/2007 | 12/17/2007 | 12/17/2007 | P | FAIL |
Steven Webb
|
|
|
Mud and dirt trackout, no signage, no dumpster. Verbal to rp;
|
Issue & PRINT permit SFD | | | 9/19/2007 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 9/13/2007 | | 9/13/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - Erosion and Sediment | 8/29/2007 | | 8/29/2007 | | FAIL |
|
|
|
ESC plan failed. No full size set of ESC drawings included with submittal. Contacted PD.
|
Application received | | | 8/22/2007 | | |
|
|
|
|