Site Final | 9/10/2008 | 9/10/2008 | 9/10/2008 | P | PASS |
Mike Jordan
|
|
|
Site is clean. All sitework and landscaping completed. 70% reveg has been achieved.
|
General Inspection | 8/21/2008 | 8/21/2008 | 8/21/2008 | A | PART |
Bob Reichert
|
|
|
looked ok
|
Conference | 5/29/2008 | 5/29/2008 | 5/29/2008 | A | DONE |
Clint A Smith
|
|
|
Met with the RP over his project area and went over the issues pertaining with the project and how to deal with the issues at hand and potential issues through the time of construction. CAS #460
|
Random Inspection | 5/1/2008 | 5/1/2008 | 5/1/2008 | P | PASS |
Clint A Smith
|
|
|
Site looks good. In issues present. CAS #460
|
Issue & PRINT permit COM | | | 3/10/2008 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 3/5/2008 | | 3/5/2008 | | PASS |
Steven Webb
|
|
|
ESC plan approved with addendun and attached conditions.
|
Routing - Erosion and Sediment | 2/28/2008 | | 2/28/2008 | | FAIL |
Steven Webb
|
|
|
ESC plan submitted is an 2005 plan for the development. Plan is needed for the proposed vertical construction. Specific to the project.
|
Routing - Erosion and Sediment | 1/8/2008 | | 1/8/2008 | | FAIL |
Steven Webb
|
|
|
No ESC narrative submitted. No plan review can be performed
|
Application received | | | 12/21/2007 | | |
|
|
|
|