General Inspection | 9/17/2008 | 9/17/2008 | 9/17/2008 | | DONE |
Troy James
|
|
|
Already finaled
|
Site Final | 9/17/2008 | 9/17/2008 | 9/17/2008 | P | PASS |
Steven Webb
|
|
|
|
Site Final | 9/2/2008 | 9/2/2008 | 9/2/2008 | A | PASS |
Clint A Smith
|
|
|
All disturbed soil is stabilized and all temporary bmps have been removed. CAS
|
General Inspection | 9/1/2008 | 9/1/2008 | 9/2/2008 | | DEFR |
Clint A Smith
|
|
|
Moved to a site final. CAS
|
Site Preparation | 6/13/2008 | 6/16/2008 | 6/16/2008 | A | PASS |
Clint A Smith
|
|
|
Site is contained. Site is looking good. They are enclosing the irragation channel into a pipe and have been working with the canal district on completing it. Water is off til Wensday. They will be complete by Wensady. CAS #460
|
Issue & PRINT permit COM | | | 6/13/2008 | | DONE |
|
|
|
|
Application received | | | 6/12/2008 | | |
|
|
|
|
Routing - Erosion and Sediment | 6/12/2008 | | 6/12/2008 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/12/2008 | | |
|
|
|
|
General Inspection | 8/15/2008 | 8/15/2008 | | | |
Steven Webb
|
|
|
|