Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberESC08-00539
StatusFinaled
Name JAY ALLRED
Site Address 6032 N FIVE MILE RD
Project Name 
Customer Number 
ePlanReview 
Description
Please attach conditions prior to issuing permit. Per phone call from Scott Hedrick-ammended acreage to add .87 for staging area per approval of Steve Webb. Fees must be paid by 6-7-09 or field inspector will issue correction notice///6-5-09 @ 9:56am BAS
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final11/4/200911/4/200911/4/2009PPASS
DetailsClint A Smith
Conference10/20/200910/20/200910/20/2009ADONE
DetailsClint A Smith
Informed the RP that there is still areas where vegitation is needed prior to finaling the permit. Once they have achieved vegitation to contact the city for a site final.
General Inspection9/17/20099/23/20099/23/2009APASS
DetailsClint A Smith
General Inspection9/17/20099/17/20099/17/2009PPART
DetailsClint A Smith
Spoke with RP over the vacent feild where the have removed all of the stock pile and graded out flat. Was told that a broadcasting of seed did occur by means of an atv. Informed RP due to the up and coming weather conditions that a sprinkler system of some sort should be used now to start to promote growth. Was told that it will be set up by 9/21/09. Will re-inspect on 9/23/09am.
General Inspection7/16/20097/16/20097/16/2009APASS
DetailsClint A Smith
Random Inspection6/29/20096/29/20096/29/2009PPART
DetailsClint A Smith
Verbal to RP:
Clean up all residual from saw cutting of parking lot. IT did not reach the storm drain inlets.
BMP Violation6/15/20096/17/20096/17/2009APART
DetailsClint A Smith
A relief trench and used exsisting wattle in areas where is over a 2% grade slope.
BMP Violation6/15/20096/15/20096/15/2009PFAIL
DetailsClint A Smith
Verbal to RP:
Protect all disturbed area with some type ofv sediment bmps along Five Mile Rd.
Protect the storm drain inlets within parking lot and the 1 storm drain at the corner of Five Mile and project area. Will re-inspect on 6/17/09.
General Inspection6/2/20096/8/20096/8/2009APART
DetailsClint A Smith
Minor tracking onto parking lot. Clean up occurs on a daily basis.
Routing - Erosion and Sediment6/5/2009 6/5/2009 DONE
DetailsBarbara Stitt
Per phone call from Scott Hedrick-ammended acreage to add .87 for staging area per approval of Steve Webb. Fees must be paid by 6-7-09 or field inspector will issue correction notice///6-5-09 @ 9:56am BAS
General Inspection6/1/20096/2/20096/2/2009AFAIL
DetailsClint A Smith
Verbal to RP:
1. Submit to the city over the additional area of disturbed area along the Eastside of project where stock pile is kept.
2. Block off access within the back section during wet conditions and clean up all tracking into the parking lot. Will re-inspect on 6/8/09 PM
Random Inspection5/4/20095/4/20095/4/2009APASS
DetailsMike Jordan
ESC permit sign posted. Controlled access is being maintained. Geneal site conditions were good.
Random Inspection4/29/20094/29/20094/29/2009APASS
DetailsMike Jordan
General Inspection4/28/20094/28/20094/28/2009PPASS
DetailsMike Kinnear
sign posted site looks fine
General Inspection4/16/20094/16/20094/16/2009APASS
DetailsJack Frank
ok
General Inspection4/14/20094/14/20094/14/2009APASS
DetailsJack Frank
ok
Tracking Control4/10/20094/13/20094/13/2009APASS
DetailsEric Strole
Tracking Control4/9/20094/10/20094/10/2009APART
DetailsEric Strole
went over construction entrance & tire wash with clint smith, will reinspect tracking 4-13-09.
Tracking Control4/9/20094/9/20094/9/2009PPART
DetailsEric Strole
left verbal correction with rp to clean up tracking in parking lot by day's end do to possible storm events. rest of site looks good. will reinspect 4-10-09
Random Inspection4/3/20094/3/20094/3/2009PPASS
DetailsClint A Smith
General Inspection3/27/20093/27/20093/27/2009APASS
DetailsJack Frank
ok
General Inspection3/4/20093/5/20093/5/2009APASS
DetailsEric Strole
Random Inspection3/3/20093/3/20093/3/2009APASS
DetailsTom Arcoraci
Random Inspection2/23/20092/23/20092/24/2009PPASS
DetailsEric Strole
Tracking Control2/13/20092/17/20092/17/2009APASS
DetailsEric Strole
tracking has been cleaned up, per steve webb next tracking violation will result in a stop work.
General Inspection2/13/20092/13/20092/13/2009AFAIL
DetailsEric Strole
left verbal correction with rp to clean up tracking by days end due to possible rain events. will reinspect on 2-16-09 am.
Tracking Control2/4/20092/6/20092/6/2009APASS
DetailsEric Strole
all corrections are complete.
Random Inspection2/4/20092/4/20092/4/2009PFAIL
DetailsEric Strole
left verbal & written correction with rp to maintain construction entrance & bmp's, clean tracking in parking lot & out to five mile,clean up small amount of trash & concrete spoil's. needs to be complete by 2-6-09 am.
Tracking Control1/21/20091/26/20091/26/2009APART
DetailsClint A Smith
RP told me that the minor concrete spoils outside of the pit will be placed into the pit by the end of the day.
Tracking Control1/21/20091/22/20091/22/2009PPART
DetailsEric Strole
talked with rp about cleaning up tracking on a daily basis due to the amount of traffic on & off project. clint smith will reinspect monday 1-25-09
Tracking Control1/21/20091/21/20091/21/2009AFAIL
DetailsClint A Smith
Verbal to RP:
Clean up all tracking off of the primary entrance. Also to clean up all concrete spoils outside of the wash out pit. Will re-inspect on 1/26/09 AM.
Random Inspection1/21/20091/21/20091/21/2009AFAIL
DetailsEric Strole
left verbal correction with rp to clean tracking in parking lot. will reinspect 1-22-09 pm
Random Inspection1/7/20091/7/20091/7/2009PPASS
DetailsClint A Smith
General Inspection12/29/200812/30/200812/30/2008APASS
DetailsClint A Smith
General Inspection12/22/200812/22/200812/22/2008PPASS
DetailsClint A Smith
General Inspection12/1/200812/5/200812/5/2008PPASS
DetailsClint A Smith
Random Inspection12/1/200812/1/200812/1/2008PPART
DetailsClint A Smith
Discussed with RP over the placement of the stock pile in the North East corner of project area. Since the stock pile mass is very large and is less than 10ft away from the hinge of the slope down to Chinden Blvd, I am requiring sediment and erosion protection on the stock pile. Will re-inspect on 12/5/08 PM.
Tracking Control11/17/200811/18/200811/18/2008APART
DetailsClint A Smith
still need to re-install wattles.
Site Preparation11/17/200811/17/200811/17/2008PFAIL
DetailsClint A Smith
Spoke with RP over the pertaining issues.
1. Clean up tracking off of both accesses on the project area. Told him to dry sweep prior to the wash into the project area.
2. Maintain all perimeter bmp's along the south end of project. #380 inspector Eric will be re-inspecting on 11/18/08.
Random Inspection11/17/200811/17/200811/17/2008AFAIL
DetailsEric Strole
left verbal correction with rp to clean tracking in parking lot & street by 11-18-08 am & repair & maintain construction entrances by 11-18-08 pm.
Tracking Control11/6/200811/7/200811/7/2008APASS
DetailsEric Strole
tracking has been cleaned up.
Random Inspection11/6/200811/6/200811/6/2008PFAIL
DetailsEric Strole
left verbal correction with rp to clean tracking in parking lot by 11-7-08 am due to possible rain events.
Tracking Control10/27/200810/27/200810/27/2008PFAIL
DetailsClint A Smith
Need to clean up loose sediment off of both access to the site. Also post a washout station sign.
Tracking Control10/13/200810/17/200810/17/2008APASS
DetailsClint A Smith
Install an additional construction access.
Tracking Control10/13/200810/13/200810/13/2008ACANC
DetailsClint A Smith
Wrong date
Random Inspection10/13/200810/13/200810/13/2008AFAIL
DetailsClint A Smith
Need to provide a construction entrance at the north end or block it off where vechile have been entering and existing. Clean up all sediment off of parking lot. Will re-inspt on 10/17/08.
General Inspection10/8/200810/8/200810/8/2008PPASS
DetailsBob Reichert
looked ok
General Inspection10/8/200810/8/200810/8/2008PPART
DetailsClint A Smith
Minor sediment off of entrance. Told RP to clean at the end of the say.
Site Preparation10/1/200810/1/200810/1/2008APASS
DetailsClint A Smith
Stop work order has been pulled.
Issue & PRINT permit COM  9/30/2008 DONE
INSP - Stop Work Order9/29/20089/29/20089/29/2008PFAIL
DetailsClint A Smith
Permit not issued. Started to clear and grub the project area. Must call for an inspection prior to stop work order being pull and any other work except for erosion and sediment control to begin.
Routing - Erosion and Sediment6/26/2008 6/26/2008 PASS
DetailsClint A Smith
ESC plan approved with attached conditions.
Application received  6/17/2008