General Inspection | 3/31/2010 | 3/31/2010 | 3/31/2010 | | DONE |
Clint A Smith
|
|
|
|
DOC - Permit Finaled | 3/31/2010 | 3/31/2010 | 3/31/2010 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 11/25/2008 | 11/25/2008 | 11/25/2008 | P | PASS |
Pat Lass
|
|
|
|
General Inspection | 10/7/2008 | 10/7/2008 | 10/7/2008 | A | FAIL |
Pat Lass
|
|
|
dirt tracking to street called rp and he said he would take care of it
|
Site Preparation | 9/26/2008 | 9/26/2008 | 9/30/2008 | P | PART |
Tony Young
|
|
|
need to maintain BMPs
|
General Inspection | 9/26/2008 | 9/26/2008 | 9/26/2008 | P | PASS |
Pat Lass
|
|
|
looked good
|
Issue & PRINT permit SFD | | | 9/17/2008 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 9/3/2008 | | 9/3/2008 | | PASS |
Clint A Smith
|
|
|
ESC plan approved with attached conditions.
|
Application received | | | 9/2/2008 | | |
|
|
|
|
Routing - Erosion and Sediment | 9/2/2008 | | 9/2/2008 | | FAIL |
Clint A Smith
|
|
|
ESC failed due to location of project in the hillside area and also the work pertaining with the project. Called the applicant and explained to them they will need to submit and erosion control plan for the project.
|