Aging Inspection | 11/26/2010 | 11/26/2010 | 11/29/2010 | | DONE |
Clint A Smith
|
|
|
|
DOC - Permit Finaled | 11/29/2010 | 11/29/2010 | 11/29/2010 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 2/9/2009 | 2/9/2009 | 2/9/2009 | P | PART |
Jim Storey
|
|
|
site looks good landscaping will be done soon.
|
General Inspection | 1/22/2009 | 1/26/2009 | 1/26/2009 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 1/23/2009 | 1/23/2009 | 1/23/2009 | P | DONE |
Bob Reichert
|
|
|
too much snow to see
|
Random Inspection | 1/22/2009 | 1/22/2009 | 1/22/2009 | A | FAIL |
Clint A Smith
|
|
|
Verbal to RP: 1. Clean up all trash debris off of lot and maintain the full debris container. 2. Clean up concrete spoil pile and dispose of it in the correct mannor. 3. Install wattle per industry standards. Will re-inspect on 1/26/09 PM
|
Random Inspection | 12/3/2008 | 12/3/2008 | 12/3/2008 | A | PASS |
Jim Storey
|
|
|
|
Random Inspection | 11/26/2008 | 11/26/2008 | 11/26/2008 | A | PASS |
Mike Jordan
|
|
|
|
Random Inspection | 11/24/2008 | 11/24/2008 | 11/24/2008 | A | PASS |
Jim Storey
|
|
|
|
General Inspection | 11/19/2008 | 11/19/2008 | 11/19/2008 | A | PASS |
Mike Kinnear
|
|
|
sign posted site looks fine
|
BMP Violation | 10/30/2008 | 10/31/2008 | 10/31/2008 | P | PART |
Clint A Smith
|
|
|
getting the issue with the notice completed at this time.
|
Complaint Inspection | 10/30/2008 | 10/30/2008 | 10/30/2008 | A | FAIL |
Clint A Smith
|
|
|
Left a message with RP.
Correction Notice: 1.Provide a trash debris container. 2. Remove all solid waste from the project area or place into a solid waste container. 3.Re-install sediment bmp's at front of project area where the slope is greater than 2% and where the disturbed soil is. 4. Clean up all hard surfaces of all sediment and debris.
|
General Inspection | 10/20/2008 | 10/20/2008 | 10/20/2008 | P | PASS |
Mike Kinnear
|
|
|
sign posted site looks fine
|
Random Inspection | 10/15/2008 | 10/15/2008 | 10/15/2008 | P | PART |
Jim Storey
|
|
|
left a message with the RP to install a sediment barrier at the front of the lot due to the slope being over a 2% grade.
|
Site Preparation | 10/14/2008 | 10/14/2008 | 10/14/2008 | | PART |
Clint A Smith
|
|
|
No work has begun, but is posted and left a message with the RP to install a sediment barrier at the front of the lot due to the slope being over a 2% grade.
|
Application received | | | 10/7/2008 | | |
|
|
|
|
Issue & PRINT permit SFD | | | 10/7/2008 | | DONE |
|
|
|
|